Black Band Distillery - Peoria, IL

August 21, 2019

Today found lead paint removal of the existing beams underway. Summit Masonry is continuing with brick repair and replacement. Coming up next week, removal of the lower level concrete floor will get started so new piping for the distillery tanks can be installed.

Prior Restoration Updates:

Black Band Distillery Structural Progress in August

Photos
Lower level floor being removed next week
Lead paint removal
Lead paint removal
Lead paint removal
Lead paint removal
Lower level floor being removed next week